DAVIS ARCHITECTS
ESTIMATED PROJECT COST
Houston-Love Memorial Library
Dothan, Alabama
Davis Architects Project #3504/A3
December 13, 2007
|
Construction Costs Site Cleaning / Demolition |
$400,000 |
|
Site Work (allowance) |
$400,000 |
|
Building (60.000 SF @ $200/$F) |
$12,000,000 |
|
Parking (150 spaces @ $2000/space) |
$300,000 |
|
Elevated Slab Over Parking (16,000 SF @ $501SF) |
$800,000 |
|
Public Plaza (14,000 SF ® 15/SF) |
$210,000 |
|
Landscape / Irrigation (allowance) |
$250,000 |
|
Sub-total |
$14,360,000 |
|
Design Contingency (@ 10% of Subtotal) |
$1,436,000 |
|
Total Construction Costs |
$15,796,000 |
|
Related Project Costs A/E Fee Base Bid (@ 6.5% of Total Construction Costs) |
$1,026,740 |
|
Site Survey (allowance) |
$6,000 |
|
Geotechnical Investigation 1 Report (allowance) |
$8,000 |
|
Materials Testing 1 Special Testing (@ .5% of Total Construction Costs) |
$78,980 |
|
LEED Cnnsu(tart (allowance) |
$50,000 |
|
HVAC / LEED Commissioning (allowance) |
$50,000 |
|
Library Shelving (® $400 per 100 Volumes fOR 240,000 Volumes) |
$960,000 |
|
Library Furnishings & Misc. Equipment (@ 5% of Building Construction Cost) |
$789,800 |
|
Meeting Room AudioVisual Equipment (allowance) |
$25,000 |
|
Reimbursable Expenses {Ad. for Bid, Printing, Travel, etc.) |
$30,000 |
|
Total Related Project Costs |
$3,024,520 |
|
TOTAL ESTIMATED PROJECT COST |
$18,820,520 |
DAVIS ARCHITECTS, INC.
120 TWENTY THIRD STREET SOUTH
205.322-7482
BIRMINGHAM, AL 35233
FAX 322-7485
WEBSITE DADOT.COM